Working with Baselines in P6 – Primavera Tips and Tricks: Tip 50
To kick off the New Year, we’ll be providing some useful tips on working with project baselines in Primavera P6. Before you update a schedule for the first time, you should create a baseline plan. The simplest baseline plan is a complete copy, or snapshot, of the original schedule. This snapshot provides a target