Primavera Tips & Tricks

Primavera P6 R8.3 Features You May Have Missed! Primavera Tips and Tricks: Tip 14

By |2018-03-07T12:09:28+10:00June 20th, 2013|Primavera Tips & Tricks|

Many of you may have had the fortune of road testing the new Primavera P6 R8.3 update. In this extract from our Primavera Support Clients’ Tips and Tricks newsletter we continue our overview of some further features and welcome enhancements. Viewing the Hierarchy for Activity, Project, and Resource Codes in Primavera P6 R8.3 To

Primavera P6 R8.3 is Here – Primavera Tips and Tricks: Tip 13

By |2018-03-07T12:19:13+10:00May 3rd, 2013|Primavera Tips & Tricks|

We’ve been road-testing the new release of Primavera P6 R8.3 and are very excited about the new features and enhancements to both Primavera P6 EPPM (web client) and Primavera P6 Professional. In this extract from our Primavera Support Clients’ Tips and Tricks newsletter we discuss some of the key features. Setting a Default Start

Resource Portlet – Primavera Tips and Tricks: Tip 12

By |2018-03-07T12:33:02+10:00April 9th, 2013|Primavera Tips & Tricks|

This extract from the Primavera Tip we shared with our Support Clients explains how to use Resource Portlet Dashboards to determine which resources are over or under allocated and ensure resources are being used effectively. Dashboards – Resource Portlets The Resource Allocation portlet in Primavera P6 is another feature that can ensure the overall

Schedule Performance Portlet – Primavera Tips and Tricks: Tip 11

By |2018-03-07T13:20:34+10:00February 11th, 2013|Primavera Tips & Tricks|

This extract from the Primavera P6 Tip we shared with our Support Clients explains how to use Dashboards to ensure all the relevant information regarding the status of a project is in one centralised location. Dashboards A common pitfall in project management is misinterpreting project information or, in some cases, even just finding information

Baselining in Primavera P6 – Primavera Tips and Tricks: Tip 10

By |2018-03-07T14:04:16+10:00November 28th, 2012|Primavera Tips & Tricks|

When creating a project schedule, prior to applying any progress to that schedule, it’s  necessary to first create a Baseline. This extract from the Primavera Tip we shared with our Support Clients explains why we need a Baseline, and shares a couple of common traps you can fall into when baselining projects. WHY BASELINE?

Exporting Layouts and Filters – Primavera Tips and Tricks: Tip 9

By |2018-03-08T14:15:06+10:00October 11th, 2012|Primavera Tips & Tricks|

In this Tip we share an extract from our update to our Primavera Support clients about how to export and import Layouts and Filters in Primavera P6. This is especially helpful if you want to share Layouts with other users or for example provide your manager with a Layout to refer to your own

Data Transfer Using Xer – Primavera Tips and Tricks: Tip 8

By |2018-03-07T14:38:54+10:00September 5th, 2012|Primavera Tips & Tricks|

Following on from last month’s post, in this extract from the monthly newsletter we provide to our Support clients, we share some tips on the capabilities and restrictions of what data can be imported and exported from Oracle Primavera P6 EPPM using the XER file format. Using the XER file format XER supports all

Data Transfer Using Excel – Primavera Tips and Tricks: Tip 7

By |2018-03-07T14:51:51+10:00August 14th, 2012|Primavera Tips & Tricks|

Importing to and exporting from Primavera P6 projects using Excel spreadsheets is a necessarily complex process but it can save you time if you are working with hundreds of activities. It’s particularly helpful, but not limited to, tasks like assigning new (or modifying existing) activity names, assigning or modifying activity resources, importing activity codes

Use the Right Date Field – Primavera Tips and Tricks: Tip 6

By |2019-04-11T11:20:28+10:00July 11th, 2012|Primavera Tips & Tricks|

With dozens of date field options in both Oracle Primavera P6 EPPM (Web Client) and Primavera P6 Professional, it can be tricky figuring out exactly which one to use at any given time. Date Fields Two date fields that often get confused are Planned Start / Finish and Early Start / Finish. For any Activity that has not

Make Sure You Summarize Regularly – Primavera Tips and Tricks: Tip 5

By |2018-03-07T15:10:13+10:00June 10th, 2012|Primavera Tips & Tricks|

In Primavera P6 Professional, the Summarize function updates a set of Summary Tables in the Primavera P6 database. These Summary Tables provide huge performance benefits for the system because they allow the user to see a list of projects, and some high-level details about them, without loading vast amounts of unnecessary activity and resource